Script Final by doaa el on Scribd
Wednesday, 28 December 2016
Saturday, 24 December 2016
Tuesday, 20 December 2016
Actor Release Form
This is the Actor Release Form template. We are planning to use this for our production, we will send it to both of our actors as a form of permission. This document should be sent off today, which means we will get the form back soon. After we get the form back fully completed it will enable us to reassure our filming dates, and start our shooting schedule.
Summary by:Doaa Elmanyneh and Zacaria Elarichi
Saturday, 17 December 2016
Shooting Schedule- Draft 1
DATE
|
SCENE
|
INT/EXT
DAY/NIGHT
|
SHOT DESCRIPTIONS SUMMARY
|
LOCATION
|
CHARACTERS
|
EQUIPMENT/PROPS/COSTUMES/ SPECIAL
REQUIREMENTS.
|
|
4TH & 5th
January 2017 26th and 27th of January if needed.
|
Shot 1 – 18
|
DAY
|
1.
Sound/ glitch
effects at the start of the music video. Duration roughly two seconds.
2.
Time lapse of
the London skyline which is shot in the Sky tower. Duration roughly two seconds.
3.
Establishing
shot showing abandoned building and or location of the scene ( Brentford
bridge)
4.
Long shot of
showing the bridge in a narrow perspective. (duration roughly 1 second)
5.
Wide angle shot
of the bridge and canal which will include gradual zoom effect.
6.
Medium close up
of main characters back looking into the water. This will include (cutting to
the beat task)
7.
Over the
shoulder/medium shot to show location of Brentford bridge.
8.
Medium shot
showing the Polaroid picture in the hand of the main actor.
9.
Low angle shot
of the actors back picking up his back pack.
10.
Medium shot of the actors back towards the
camera walking away with the back pack.
11.
Low angle shot
of the feet of or actor walking away from the initial scene through an
alleyway.
15. Wide shot of the actor walking through the alley
way
17. Another wide shot of the scenery and abandoned
surroundings around the actor.
|
Brentford Bridge
|
Ahmed
|
-
Camera
-
Tripod
-
Hoodie
-
Facemask
-
Backpack
-
Polaroid
picture
|
|
8th-9th January
2017
|
Shot 19- 35
|
Day
|
-
Camera
-
Tripod
-
Backpack
-
Face mask
-
Hoodie
|
||||
10th-11th
January 2017 (24th-25th if needed)
|
Shot 34 - 47
|
Night
|
-
Face Mask
-
Tripod
-
Camera
-
GoPro
-
Backpack
|
||||
13th – 14th
January 2017
|
60 - 81
|
Day
|
-
Camera
-
Tripod
-
Roller-skates
-
Face mask
-
Backpack
|
||||
16th- 17th
January 2017
|
81- 112.
|
Day
|
-
Face mask
-
Polaroid
picture
-
Backpack
-
Camera
-
Tripod
|
Summary by: Doaa Elmnaynrh, Jack Baxter and Zacria Elarichi
Thursday, 15 December 2016
Location Release Form
I have created this Location Release Form, we decided to do this as it will enable us to gain permission for transport filming such as inside the bus. this will be important as we have mentioned previously in our research, in order to re-ensure safe environment. We are planning to film during off-peak hours this is so we avoid large crowds, as this may result in various risks. In addition, we are planning to ask for the permission shortly this week, which will enable us to have time to plan the shooting schedule and make confident decisions about dates of filming. Not only that, but this will surely benefit our time management.
Friday, 9 December 2016
Group Work- Storyboard Final Draft
This was out final draft of the story board. We collectively discussed that there won’t need to be any additional improvement that we want to make to the storyboard due to putting a lot of time and effort in to it. We assume this is a very strong structure of the storyboard which will allow us to create a very adequate recording schedule as well as enabling us to film the scenes. There could be some improvements that we could possibly make during recording time but that all depends on how the filming goes. The main objective is to record all the shots which are shown below. However that doesn't mean we have to follow the plan and limit ourselves to the minimum as we can record other shots which possibly can help us during the editing process. This would save us a lot of time instead of going back to the locations and redo the shooting parts as we can just use the extra shots we have filmed which are not in the story board.
Additionally, within our storyboard, we have included detailed notes about the shots that we have chosen and their effect. The annotation of each shots are developed even more in the script. We have also made a timeline assisting us as it will tell us when we want our shots to start and finish. This is useful as it would help us a lot in the editing process.
Summary by: Doaa Elmnayneh, Jack Baxter, Zacaria Elarichi and Momeena
Monday, 5 December 2016
Thursday, 1 December 2016
Group Work- Budget Improvment
Below is the first attempt at creating our budget, The budget is an important piece if information in which we will need to contemplate while making the music video and therefore I have created a excel document in which shows us the different costs that will be involved while making the video. I have chosen to use Microsoft excel as this is a programme in which I believe allows me to best share this information. The Miscellaneous tab is purely for the flare and the other props which will need to be brought at a later date. Overall this task has allowed us to create a budget which will allow us to get a guideline upon how much money we will need to spend each when venturing out on these dates. When buying the flare the total price was £12, the contribution per group member was
Doaa:£4
Zacaraia:£4
Jack:£4
Momeena:£0
Summary by: Jack Baxter
Subscribe to: